William St., Schatzell St., & Starr St. - Marina Arts District in Corpus Christi, TX

May 31, 2017


Ahead of the Chaparral Street Phase II bond project, work will begin June 5th on the following side streets:

  • William Street:
    • June 5th – Mill from Chaparral to Water
    • June 6th – Mill from Chaparral to Mesquite
    • June 7th – Prep work from Chaparral to Water and from Chaparral to Mesquite
    • June 8th – Pave from Chaparral to Water
    • June 9th – Pave from Chaparral to Mesquite
    • June 12th – Striping from Chaparral to Water
    • June 13th – Striping from Chaparral to Mesquite
  • Schatzell Street:
    • June 14th – Sweep, clean and seal coat from Chaparral to Water
    • June 15th – Sweep, clean and seal coat from Chaparral to Mesquite
    • June 16th – Stripe from Chaparral to Water
    • June 19th – Strip from Chaparral to Mesquite
  • Starr Street:
    • June 19th – Start sweep, clean and seal coat from Chaparral to Water
    • June 20th – Sweep, clean and seal coat from Chaparral to Water
    • June 21st – Sweep, clean and seal coat from Chaparral to Mesquite
    • June 22nd – Stripe from Chaparral to Water
    • June 23rd – Stripe from Chaparral to Mesquite

Work may require portions of these streets to be closed during the scheduled time frames. There will be parking restriction enforcement during each construction zone time frame.

For more information, contact Traffic Engineering at (361) 826-3547.