Jun 9, 2017


The Chaparral Street Phase II bond project is due to start around September of this year and, in preparation for that project, work began June 5th on William Street to provide additional parking to replace bays suspended during the phase II work:

William Street: Two other streets, Schatzell and Starr will have similar work performed on them and that schedule is listed below:

  • Schatzell Street:
    • June 14th – Sweep, clean and seal coat from Chaparral to Water
    • June 15th – Sweep, clean and seal coat from Chaparral to Mesquite
    • June 16th – Stripe from Chaparral to Water
    • June 19th – Strip from Chaparral to Mesquite
  • Starr Street:
    • June 19th – Start sweep, clean and seal coat from Chaparral to Water
    • June 20th – Sweep, clean and seal coat from Chaparral to Water
    • June 21st – Sweep, clean and seal coat from Chaparral to Mesquite
    • June 22nd – Stripe from Chaparral to Water
    • June 23rd – Stripe from Chaparral to Mesquite